eKanban Setup Process

<< Click to Display Table of Contents >>

Navigation:  PFEP >

eKanban Setup Process

The following outlines the procedure for making eKitting operational with scanners.

1.Import BOM data

2.Create Locations and Supply Systems

3.Create Containers, Container Classes, and Container Types

4.Create Locations and Supply Systems

5.Create Part Plans using the previously imported BOM data

6.Print Cart Labels and Rack Labels

a.Make sure that the printer being used has a high enough resolution for barcodes. Run a quick scanning test to confirm this

7.Publish Part Plan Data and BOM Data

8.Place Labels on containers and racks