The Workstep import is used to update one or more Activity's worksteps en masse by replacing the current data with the imported data. Many fields are not required to import worksteps, but are used to show details within the activity.
Workstep Standard Fields
Field |
Description |
Mandatory to Import |
ActivityID |
This is used to map the workstep to an existing activity by ID number. |
Yes |
Description |
A description for the item being imported. This field can be up to 512 characters long or it may be left blank. |
No |
Step No |
If left blank will be defaulted to "0.00" |
No |
PlantID |
The process is added to the plant whose ID is specified. Many users only have one plant set up in their Assembly Planner system; if you are unsure as to the ID, check in the Library > Plant Tab. |
Yes |