Action(s) to be performed by ME |
a.Copy new part from EBOM and 'paste as sibling' in MBOM. b.Set the From Date on the copied Item. |
Example: ECO-0001 says Add C1 under P1
a.After ME performs the action(s) specified above, the MBOM looks like:
P1
l C1 (From: 15-JUN-2010 To 31-DEC-2030)
NOTE:
i.The MCO From Date chosen by the ME is 15-JUN-2010
b.After the MCO for this ECO is promoted to Implement Status, the data is exported to the MRP system. The BOM file would contain the following record(s) for the above change(s) performed by the ME:
Parent Item |
Child Item |
From Date |
To Date |
P1 |
C1 |
15-JUN-2010 |
31-DEC-2030 |